Public Storage (via Forza Services) — 385 Gerard Avenue, Bronx — Self-Storage

Featured project · In progress — completion scheduled December 2026

43indoor units
5Daikin VRV EMERION systems
9outdoor modules
12floors, roof down

The Situation

This 12-story self-storage facility was conditioned by seven rooftop VRF systems on an Intelligent Touch Manager. Mountain Mechanical has serviced the site since August 2025. The record shows recurring thermistor, electrical and circuit-board failures, and a master-unit setup that had never been completed at turnover. By June 2026, every floor except the 5th was without HVAC.

Why Replace, Not Repair

We kept the building running with repairs for a year and documented every failure in a full service history. Once the failures had spread to nearly every floor, we recommended replacement and designed the new system with Daikin’s VRV team.

The New System

  • 5 Daikin VRV EMERION heat-pump systems on 9 outdoor modules
  • 43 Daikin indoor units across all 12 floors, including the lobby, each with its own Daikin remote controller
  • A Daikin SkyAir system for the elevator machine room
  • Existing duct risers reused to limit disruption, with the building open to customers throughout

How the Job Is Run

  • Roof down, one floor at a time: every scope on a floor is finished and signed off before the crew moves down
  • Press fittings on refrigerant and condensate piping, so there is almost no open-flame work inside an occupied storage building
  • EPA refrigerant recovery, pressure-test and evacuation logs kept for every system
  • Written SOP, site safety manual, daily toolbox talks, sign-in book, daily progress reports and before/after photos every day
  • NYC DOB permit issued October 27, 2026 and renewed November 12, 2026
  • Licensed industrial hygienist and a restoration contractor brought in within 24 hours when the owner raised floor-condition concerns
  • Crane lift of the outdoor modules over the roof edge, with the parking lot closed for safety

Status

Floor work is moving from the 12th floor down, with startup, commissioning and turnover to follow. Completion is scheduled for December 2026. We will update this page with finished photos.

See the demolition photo log → Ten photos, in order, from roof and elevator protection through unit removal and floor clean-up.

“When replacement is the right call, the work is planned carefully, executed cleanly, and closed out on schedule.”Jim Macaluso, Forza Services · read the signed letter (PDF)

Project Details

  • Owner: Public Storage, managed through Forza Services
  • Location: Mott Haven, Bronx
  • Building: 12-story self-storage facility
  • New systems: Daikin VRV EMERION (5 systems, 9 modules, 43 indoor units), Daikin SkyAir
  • Service: Service history, full replacement, permitting, rigging
  • Timeline: Service since August 2025; replacement October–December 2026
NYC DOB work permit issued to Peter Montana, Mountain Mechanical NY
NYC DOB work permit issued to Peter Montana, Mountain Mechanical NY
Roof protected with boards, tarps and sandbags before demolition
Roof protected with boards, tarps and sandbags before demolition
Elevator cab padded before any equipment moves through the building
Elevator cab padded before any equipment moves through the building

Have a VRF system other contractors can’t fix?

Mountain Mechanical diagnoses and repairs Daikin, Mitsubishi, LG, Samsung and Fujitsu VRF systems across NYC, Long Island and Westchester. See how our VRF repair and rescue service works, or call 833-504-4822.

← All case studies

Need a technician? Mountain Mechanical provides VRF repair and rescue service for systems other contractors haven’t been able to fix, across NYC, Long Island and Westchester. Call 833-504-4822.