These photos follow the demolition of the original equipment at 385 Gerard Avenue in the Bronx, in the order the work was done. Before anything was removed, our crew protected the roof, padded the elevator cabs and covered the storage lockers under each work area. Units then came down one at a time, were stacked and staged out of customer aisles, and every area was cleaned before the crew moved on. The building stayed open to customers the whole time.
1. Protect Roof protected with boards, tarps and sandbags before demolition2. Protect Elevator cab padded before any equipment moves through the building3. Prepare Lift brought in only after the elevators were protected4. Before An original ceiling-hung indoor unit before removal5. Protect Locker tops covered with heavy plastic under the work area6. Remove Unit lowered by hand, under control, over a protected locker7. Remove Unit off, opening ready for the new Daikin equipment8. Remove Removed units stacked on a cart for a single trip out9. Remove Old equipment staged for removal, out of customer aisles10. Clean up Aisle swept and cleaned before the crew moves to the next area
Need a technician? Mountain Mechanical provides VRF repair and rescue service for systems other contractors haven’t been able to fix, across NYC, Long Island and Westchester. Call 833-504-4822.